Timeline - SIP

Please note this schedule is subject to change.
- Future Events
- No future events scheduled
- Past Events
- 12 November 2018: ACF SIP friendly user period started with two UTHSC projects and one UTK project
- 12 November 2018: ACF SIP production start date
- 30 October 2018: Friendly-user period invitations sent to prospective PIs
- October 2018: Bastion host sip-bh1 configured
- 31 August 2018: SIP Authority to Operate conferred
- 23 Aug 2018: Skylake compute nodes installed into SIP
- 10 Aug 2018: SIP networking installed and configured for SIP by OIT
- 31 July 2018: SIP networking gear racked
- 16 July 2018: SIP equipment physically moved from JICS 116 to KPB Data Center
- March 2018: SIP equipment physically moved from K200 to JICS 116